Decision Maker: Planning Control Committee
Decision status: For Determination
Is Key decision?: No
Is subject to call in?: No
RESOLVED: That application 22/03092/FP be GRANTED planning permission subject to the reasons and conditions set out in the report of the Development and Conservation Manager as amended by the Supplementary agenda, with the following additional condition:
“Condition 28:
Prior to the commencement of the development hereby approved, a scheme of sensitively designed lighting strategy shall be submitted to and approved in writing by the Local Planning Authority. The lighting scheme shall include and consider temporary construction lighting as well as more permanent lighting associated with the development hereby approved. Light-spill (including from temporary construction lighting) onto retained and newly created habitat, in particular the retained woodland habitat forming the south of the site, should be minimised in accordance with good practice guidance, as set out in footnote 15 of the approved Updated Ecological Report by Aspect Ecology referenced 1005083 UEcoAp vf12 CL dated 15/11/2022. The sensitively designed lighting strategy shall consider the following key factors:
• Light exclusion zones
• Variable Lighting Regimes
• Light barriers
• Spacing and height of lighting units
• Light intensity
• Directionality
Reason: To ensure the protection, enhancement and management of biodiversity, and to comply with Policy NE4 of the North Hertfordshire Local Plan 2011 to 2031.”
Report author: Sarah Kasparian
Publication date: 16/10/2023
Date of decision: 12/10/2023
Decided at meeting: 12/10/2023 - Planning Control Committee