Decision Maker: Planning Control Committee
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
RESOLVED: That application 22/03231/FP be REFUSED planning permission, contrary to the officer recommendation, subject to the following reasons:
(1) The proposal would be inappropriate development within the Green Belt that would be harmful to its openness. The Council considers that the benefits of the scheme, including the wider environmental benefits associated with the increased production of renewable energy (pursuant to paragraph 156 of the National Planning Policy Framework December 2023), would not amount to very special circumstances sufficient to outweigh the harm to the Green Belt by reason of inappropriateness and other harm. As such the proposal would be contrary to paragraphs 152 and 153 of the National Planning Policy Framework and Policy SP5 of the North Hertfordshire Local Plan 2011-2031.
(2) The proposal would result in harm to the rural character and appearance of the application site and the surrounding area with a cumulative impact as a result of other major development in the vicinity. Whilst measures are proposed to mitigate the impact of the proposed development, and the proposal would not be permanent, there would nevertheless be harm over a long period to rural character and appearance of the area, including the visual amenities of users of the local public footpaths. The proposal would therefore conflict with Policies NE2 and NE12 of the North Hertfordshire Local Plan 2011-2031, which seek to avoid unacceptable harm to landscape character and appearance.
Report author: Sarah Kasparian
Publication date: 19/07/2024
Date of decision: 18/07/2024
Decided at meeting: 18/07/2024 - Planning Control Committee