Decision Maker: Finance, Audit and Risk Committee
Decision status: For Determination
Is Key decision?: No
Is subject to call in?: No
RECOMMENDATION TO CABINET: That Finance, Audit and Risk Committee comment on the recommendations to Cabinet which are:
(1) That Cabinet notes the forecast expenditure of £26.366M in 2025/26 on the capital programme, paragraph 8.3 refers.
(2) That Cabinet approves the adjustments to the capital programme for 2026/27, as a result of the revised timetable of schemes detailed in table 2 and 3, increasing the estimated spend by £1.773M.
(3) That Cabinet notes the position of the availability of capital resources, as detailed in table 4 paragraph 8.6 and the requirement to keep the capital programme under review for affordability.
REASON FOR RECOMMENDATION: Cabinet is required to approve adjustments to the capital programme and ensure the capital programme is fully funded.
Report author: Dean Fury
Publication date: 09/01/2026
Date of decision: 07/01/2026
Decided at meeting: 07/01/2026 - Finance, Audit and Risk Committee
Accompanying Documents: