Decision status: Deleted
Is Key decision?: Yes
Is subject to call in?: No
RECOMMENDED TO CABINET:
(1) That the Third Quarter Revenue Monitoring 2019/20 be noted:
(2) That the changes to the 2019/20 General Fund Budget, as identified in table 3 and paragraph 8.2, a £262k in net expenditure be approved;
(3) That the changes to the 2020/21 General Fund budget, as identified in table 3 and paragraph 8.2, a £287k in net expenditure be approved.
REASON FOR DECISIONS:
Members are able to monitor, make adjustments within the overall budgetary framework and request appropriate action of Services who do not meet the budget targets set as part of the Corporate Business Planning process.
Report author: Ian Couper
Publication date: 18/03/2020
Date of decision: 16/03/2020
Decided at meeting: 16/03/2020 - Finance, Audit and Risk Committee
Accompanying Documents: