Decision Maker: Planning Control Committee
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
· Removal of Condition 21 as detailed in the report.
· Condition 22 and Condition 23 to become Condition 21 and Condition 22 respectively.
· Additional Conditions 23 and 24 to read:
“Condition 23
The development permitted by this planning permission shall be carried out in accordance with the following documents:
· E-mail response dated 23 August 2022 from Nolan Associates
· E-mail response dated 28 October 2022 from Nolan Associates
· Drainage Strategy carried out by Nolan Associates dated March 2022 reference 2021- 087
· CCTV and Connectivity Survey dated 9 May 2022 carried out by Wrc
· Manhole Survey Report dated 27 May 2022 carried out by Wrc
and the following mitigation measures:
1. Provide minimum surface water attenuation volume of 27m3 to ensure no increase in surface water run-off volumes for all rainfall events up to and including the 1 in 100 year + climate change (40%) event.
2. Implement drainage strategy based on a tank and permeable paving for attenuation and treatment at a discharge rate of 2l/s into an existing surface water sewer (final details to be confirmed as part of a post demolition condition).
3. Provide water quality treatment using permeable paving on 10 parking bays where all the impermeable areas including the access road will be directed to the permeable paving for treatment prior to discharge.
Reason To prevent flooding by ensuring the satisfactory storage of/disposal of surface water from the site.
Condition 24
No development shall take place, apart from the demolition of the current building, until the final design of the drainage scheme is completed and is approved by the LPA. The surface water drainage system will be based on the following approved documentation:
· E-mail response dated 23 August 2022 from Nolan Associates
· E-mail response dated 28 October 2022 from Nolan Associates
· Drainage Strategy carried out by Nolan Associates dated March 2022 reference 2021- 087
· CCTV and Connectivity Survey dated 9 May 2022 carried out by Wrc
· Manhole Survey Report dated 27 May 2022 carried out by Wrc
The scheme shall also include:
1. Post demolition survey of the existing drainage system to confirm the existing connection into a sewer. Should the survey determine the connection is into an existing combined sewer, the applicant will need to demonstrate that they have considered other options where possible to connect into another surface water sewer.
2. Permission from Anglian Water to connect into their sewer including any required sewer upgrades due to capacity issues at the agreed rate of 2l/s.
3. Detailed engineered drawings of the proposed SuDS features including their location, size, volume, depth and any inlet and outlet features including any connecting pipe runs and all corresponding calculations/modelling to ensure the scheme caters for all rainfall events up to and including the 1 in 100 year + 40% allowance for climate change event.
4. Detailed engineered drawings of the tank and permeable paving parking areas. The drawing should also show proposed levels of how the access road and other hardstanding areas will drain into the permeable paved parking bays.
5. Demonstrate appropriate SuDS management and treatment and inclusion of above ground features such as permeable paving, reducing the requirement for any underground storage.
6. Provision of half drain down times for surface water drainage within 24 hours.
7. Silt traps for protection for any residual tanked elements.
Reason: To prevent flooding by ensuring the satisfactory storage of and disposal of surface water from the site.”
Report author: Anne McDonald
Publication date: 05/12/2022
Date of decision: 01/12/2022
Decided at meeting: 01/12/2022 - Planning Control Committee