88 3RD QUARTER MONITORING REPORT ON KEY PROJECTS FOR 2021-22 PDF 263 KB
An update on projects to support delivery of
the Council Plan 21-26
Additional documents:
Decision:
RESOLVED: That delivery against the key projects for 21/22 was noted and commented on by the Overview and Scrutiny Committee.
REASON FOR DECISION: To enable achievements against the key projects for 2021/22 to be considered.
Minutes:
Audio recording – 16 minutes 26 seconds
The Controls, Risk and Performance Manager presented the report entitled ‘3rd Quarter Monitoring Report on Key Projects for 2021-22’ and advised of the following:
· In this report there were 7 green projects, 4 amber and 2 completed.
· The renovation of Howard Park play area and the refurbishment of lists at Lairage Car Park were completed and would be removed from future monitoring report.
· No update had been received on the Local Plan.
· Preparation of the Cycling and Walking Strategy had moved to amber as this was taking longer than expected.
· Consultation was due to be conducted by Herts County Council consultants in March 22, prior to adoption by the HCC Highways and Transport Panel.
· A full list of projects was included at Appendix A.
Councillor David Levett, as Chair, proposed and Councillor Jim McNally seconded and, following a vote, it was:
RESOLVED: That delivery against the key projects for 21/22 was noted and commented on by the Overview and Scrutiny Committee.
REASON FOR DECISION: To enable achievements against the key projects for 2021/22 to be considered.