Year end 2021-22 (Q4) Project Monitoring

Meeting: 13/06/2022 - Overview and Scrutiny Committee (Item 106)

106 END OF YEAR MONITORING REPORT ON KEY PROJECTS FOR 2021 - 22 pdf icon PDF 271 KB

Additional documents:

Decision:

RESOLVED: That delivery against the key projects for 2021-2022 was noted and commented on by the Overview & Scrutiny Committee and that those marked as completed can be removed from future reports.

 

REASON FOR DECISION: To enable achievements against the key projects for 2021/22 to be considered.

Minutes:

Audio recording – 40 minutes 50 seconds

 

The Controls, Risk and Performance Manager presented the report entitled ‘End of Year Monitoring Report on Key Projects for 2021-22’ and advised Members of the following:

 

·         This report covered to the end of March 2022 and contained 3 completed and 7 amber projects. The items marked as completed would no longer be reported to this Committee.

·         All trees for the Tree Giveaway project had now been distributed.

·         Some projects had moved from green to amber during this quarter, for example the provision of housing at market rent, the trial of EV charging points in North Herts and the disposal of surplus land. The report detailed where these projects were at currently.

·         The Local Plan was still outstanding, however an update had been received with advice that the draft report had been passed onto the Department for Levelling Up, Housing and Communities and will then go through a final audit, before returning to the Council for fact checking ahead of final publication.

 

In response to a question from Councillor David Levett, the Controls, Risk and Performance Manager advised that no idea of timeline had been provided in connection with the Local Plan.

 

Councillor Levett noted that the 9 June 2017 was the date the Plan was submitted, so this marked the 5th anniversary.

 

Councillor Claire Strong proposed and Councillor Adam Compton seconded and, following a vote, it was:

 

RESOLVED: That delivery against the key projects for 2021-2022 was noted and commented on by the Overview & Scrutiny Committee and that those marked as completed can be removed from future reports.

 

REASON FOR DECISION: To enable achievements against the key projects for 2021/22 to be considered.