Issue - meetings
STRATEGIC PLANNING MATTERS
Meeting: 27/06/2023 - Cabinet (Item 195)
195 STRATEGIC PLANNING MATTERS
PDF 442 KB
REPORT OF THE SERVICE DIRECTOR – REGULATORY
This report identifies the latest position on key planning and transport issues affecting the District.
Additional documents:
- Appendix A - Project Board Terms of Reference.pdf, item 195
PDF 204 KB
- Appendix B - North Hertfordshire Masterplanning Principles.pdf, item 195
PDF 302 KB
- Appendix C - Policy SP9 Approval Process.pdf, item 195
PDF 250 KB
- Appendix D - Design Review Protocol.pdf, item 195
PDF 187 KB
- Appendix E - Member Involvement Protocol.pdf, item 195
PDF 122 KB
- App F - 140223 North Herts Council response to Wallington NP Reg 14 Consultation.docx, item 195
PDF 852 KB
- App G - North Herts response - Levelling-up and Regeneration Bill reforms to national planning policy.pdf, item 195
PDF 221 KB
Decision:
RESOLVED:
(1) That the report on strategic planning matters was noted.
(2) That the officer responses and Project Board procedures attached as Appendices A to G were noted and endorsed by Cabinet.
(3) That Cabinet approved the use of £85k of reserve funding to respond to the London Luton Airport planning application being considered by the Planning Inspectorate.
REASON FOR DECISION: To keep Cabinet informed of recent developments on strategic planning matters.
Minutes:
Audio recording – 1:16:34
Councillor Ruth Brown presented the report entitled ‘Strategic Planning Matters’ and advised:
· The report took into consideration the LCWIP and Conservation Areas.
· The proposed timetable for the remaining Strategic Planning Documents (SPDs) were detailed in the report, which were Sustainability, Biodiversity and Design Code.
· There were six large strategic sites. The first, Highover Farm was being presented to the Planning Control Committee on 6 July 2023.
· Paragraph 8.13 detailed the Ickleford Neighbourhood Plan Consultation, which would be reported on.
· Paragraph 8.16 detailed the Chesfield Consultation, which had lots of resident representation. However, further discussions would take place, as key stakeholders were not involved.
· Paragraphs 8.32 and 8.33 detailed the recommendation to approve £85k to respond to the Development Consent Order from London Luton Airport.
· The Council had made an in-principle objection, and the joint response would be made with Hertfordshire County Council (HCC) and Dacorum Borough Council.
· Paragraph 8.42 detailed bus service improvement. HCC had been given a significant sum of money to go towards fare reduction and priority buses in Hitchin.
· Paragraph 8.52 detailed Electric Vehicle Charging Points, which was currently awaiting funding from the Office for Zero Emission Vehicles.
· If funding was unsuccessful, there could be alternative funding from HCC through the Government Local Electric Vehicles Infrastructure (LEVI) capital fund programme.
Councillor Ruth Brown proposed and Councillor Amy Allen seconded and, following a vote, it was:
RESOLVED:
(1) That the report on strategic planning matters was noted.
(2) That the officer responses and Project Board procedures attached as Appendices A to G were noted and endorsed by Cabinet.
(3) That Cabinet approved the use of £85k of reserve funding to respond to the London Luton Airport planning application being considered by the Planning Inspectorate.
REASON FOR DECISION: To keep Cabinet informed of recent developments on strategic planning matters.