Skip to main content

Issue - meetings

25/02571/OP - GROWING BALDOCK DEVELOPMENT SITE - BA1 (LAND EAST OF NORTH RD AND NORTH OF RAILWAY LINE); BA10 (LAND BETWEEN RAILWAY LINE AND ROYSTON RD); BA3 (LAND WEST OF A505); BA2 (LAND SOUTH OF CLOTHALL RD); Walls Field; Urban Open Land West Of A5

Meeting: 22/10/2026 - Planning Control Committee (Item 6.)

6. 25/02571/OP - GROWING BALDOCK DEVELOPMENT SITE - BA1 (LAND EAST OF NORTH RD AND NORTH OF RAILWAY LINE); BA10 (LAND BETWEEN RAILWAY LINE AND ROYSTON RD); BA3 (LAND WEST OF A505); BA2 (LAND SOUTH OF CLOTHALL RD); Walls Field; Urban Open Land West Of A505, And Land West Of North Rd, Baldock pdf icon PDF 2 MB

REPORT OF THE DEVELOPMENT AND CONSERVATION MANAGER

 

Growing Baldock Development Site: Outline planning application with all matters reserved except for means of highway access into the development from North Road and Clothall Road for: up to 3,200 homes, up to 16ha of employment, waste and leisure infrastructure, a mixed use local centre, up to 1 secondary school, up to 2 x primary schools, nursery/childcare facilities, health hub, green infrastructure (including parks, formal sports provision, play, habitat areas, informal open space and structural planting), internal street network, access junctions and railway crossing, public transport infrastructure, pedestrian/cycle network (including PRoW diversions, active travel routes, mobility hubs and crossing of the railway), utilities and drainage infrastructure (including diversions of existing and provision of new infrastructure, pumping stations, sustainable drainage, primary substations, rising main/strategic sewer and renewable energy infrastructure), ground remodelling/earthworks and any necessary demolitions (as amended).

 

Additional documents:

Decision:

RESOLVED: That application 25/02571/OP be GRANTED planning permission subject to:

 

A)          The completion of a satisfactory legal agreement (which will provide priority towards increasing affordable housing provision, which should be onsite where possible, before consideration is given to any other planning obligations with the viability review mechanisms) and the applicant agreeing to extend the statutory period in order to complete the agreement; and

 

B)          Providing delegated powers to the Development and Conservation Manager to (i) resolve outstanding matters including financial contributions and (ii) update conditions and informatives with minor amendments as required, including the addition of informatives pertaining to North Herts Council Member representation on the stewardship body for open space, and the expectation for all roads to be constructed to an adoptable standard and adopted by Hertfordshire County Council Highways; and

 

C)          The conditions set out in the report of the Development and Conservation Manager, with the following additional Conditions 24 and 25, amendments to Definition 2 and Conditions 3, 6, 23, 34 and 36, and the renumbering of Conditions 62 and 63 (previously Conditions 24 and 25):

 

‘Definition 2

 

“Enabling Works” shall refer to preparation works to make the site ready for construction. Such works include (but are not exclusively limited to) site or ground clearance and preparation; surveying; environmental and hazardous substance testing and sampling; soil tests; remediation works; pegging out; tree protection; ecological survey and mitigation works; archaeological investigation; site clearance; ground improvement works; construction of boundary fencing or hoardings including for site security, demolition and removal of buildings and other structures; creation of temporary haul roads and enabling works to accesses or other works or operations to enable any of these works to take place including ground and site works.

 

Condition 3

 

Development shall not commence, except for Enabling Works, development within BA2 and the approved accesses shown on the approved access plans set out in Condition 5, unless:

 

·             It falls within a Phase and an approved Reserved Matters Area; or

·             The proposed development is identified as development advanced outside a Phase in accordance with Condition 8.

 

Reason: For the avoidance of doubt and to secure comprehensive, coordinated and sustainable development and to ensure that infrastructure provision and environmental mitigation are provided in time to cater for the needs and impacts arising from development in accordance with Policies SP1 and SP9 of the North Hertfordshire Local Plan (2022).

 

Condition 6

 

The development hereby permitted shall be carried out wholly in accordance with the supporting approved documents and plans listed below:

 

UAC092-001-RevF

PC7029-ITP-CE-GB-DR-D-0150-P01

PC7029-ITP-CE-GB-DR-D-0152-P02

 

Reason: To ensure the development is carried out in accordance with details which form the basis of this grant of permission.

 

Condition 23

 

No demolition/development shall take place/commence until an Archaeological Written Scheme of Investigation has been submitted to and approved by the local planning authority in writing. The scheme shall include an assessment of archaeological significance and research questions; and:

 

1.           The programme and methodology of site investigation and recording.

2.           The programme and methodology of site investigation and recording, preservation  ...  view the full decision text for item 6.