Q1 20/21 Key Projects

Meeting: 08/09/2020 - Overview and Scrutiny Committee (Item 45)

45 1ST QUARTER MONITORING REPORT ON KEY PROJECTS FOR 2020/21 pdf icon PDF 232 KB

REPORT OF THE CONTROLS, RISK AND PERFORMANCE MANAGER

To consider the quarterly update on progress of key projects to support delivery of the Council Plan 2020-24

Additional documents:

Decision:

RESOLVED:

 

(1)       That delivery against the key projects for 20/21 be noted;

 

(2)       That monitoring of the project to provide a purpose-built depot, transfer facility and household waste recycling centre be removed from the monitoring report for 2020/21 and that monitoring resume in 2021/22.

 

REASON FOR DECISIONS: To enable achievements against the key projects for 2020/21 to be considered.

Minutes:

Audio recording – 1 hour 13 minutes 1 second

 

The Controls, Risk and Performance Manager presented the report entitled 1st Quarter Monitoring on Key Projects for 2020/21 together with the following appendix:

 

·                Appendix A - 1st Quarter Monitoring against Key Projects 2020/21.

 

She drew attention to the following:

 

·                The Local Plan virtual Examiner Hearings would take place between 28 September 2020 and 19 October 2020;

·                The Planning Inspector’s hearing regarding the crematorium would be held on 27 October 2020;

·                The purpose-built depot, transfer facility and household waste recycling centre was delayed for at least 12 months and it was proposed that this be removed from the monitoring report for 2020/21 and that monitoring resume in 2021/22.

 

The following Members took part in the debate and asked questions:

 

·                Councillor Terry Hone;

·                Councillor Martin Stears-Handscomb.

 

RESOLVED:

 

(1)       That delivery against the key projects for 20/21 be noted;

 

(2)       That monitoring of the project to provide a purpose-built depot, transfer facility and household waste recycling centre be removed from the monitoring report for 2020/21 and that monitoring resume in 2021/22.

 

REASON FOR DECISIONS: To enable achievements against the key projects for 2020/21 to be considered.