Agenda item

WASTE, RECYCLING AND STREET CLEANSING CONTRACT SERVICE DESIGN - PART 2

REPORT OF THE SERVICE DIRECTOR – PLACE

 

To inform Cabinet that officers are currently undergoing a competitive dialogue procurement and are seeking a decision from Cabinet on further service design options that can be considered in order to achieve the long[1]term financial sustainability of the service and the Council.

Decision:

RESOLVED:

 

(1)   That Cabinet agreed the service changes described in 8.2 c) of the report relating to the three-weekly collection of separated paper and cardboard predominantly in bins and the three weekly collection of the remaining dry mixed recycling (A 3,3,3 cycle as described in Appendix 3) be implemented as part of the new waste recycling and street cleansing contract which commences in 2025, the implementation date shall be delegated to the Service Director: Place in consultation with Project Board (in any event to be within four months of contract commencement).

 

(2)   That Cabinet agreed that in the event that the Council is required to make a decision to provide fortnightly collection of residual waste that the dry recycling service shall be fully commingled.

 

(3)   That Cabinet agreed the service changes described in 8.2 d) of the report relating to the removal of the requirement for a continuous street cleansing presence in town centres and moving the back to standard time to 9am be implemented as part of the new waste recycling and street cleansing contract in 2025.

 

(4)   That Cabinet agreed the service changes described in 8.2 e) relating to a removal of approximately 30% of litter bins from predominantly outside the town centres be implemented during the mobilisation of new waste recycling and street cleansing contract for 2025.

 

(5)   That Cabinet agreed the service changes described in 8.2 f) relating to a change to an input specification for high-speed road cleansing to once per year be implemented as part of the new waste recycling and street cleansing contract in 2025.

 

(6)   That Cabinet agreed the service changes described in 8.2 g) relating to the removal of dedicated seasonal leaf fall management be implemented as part of the new waste recycling and street cleansing contract in 2025.

 

(7)   That Cabinet agreed the service changes described in 8.2 h) relating to an extension of the bin delivery/repair Service Level Agreement (SLA) from 5 days to 9 days being implemented as part of the new waste recycling and street cleansing contract in 2025.

 

(8)   That Cabinet agreed the service changes described in 8.2 i) relating to an extension of the missed bin rectification SLA from 5pm the next working day to 72 hours except for missed whole streets which will remain 5pm the next working day, being implemented as part of the new waste recycling and street cleansing contract in 2025.

 

(9)   That Cabinet agreed the service changes described in 8.2 j) relating to a change in street cleansing SLAs being implemented as part of the new waste recycling and street cleansing contract in 2025.

 

(10)         That Cabinet agreed the service changes described in 8.2 k) relating to reducing the number of items collected as part of bulky waste services from six to three being implemented as part of the new waste recycling and street cleansing contract in 2025.

 

(11)         That Cabinet noted that the Capital expenditure identified in 10.3 of this report will need to be added to the Capital programme as part ofthe 2024/25 budget process.

 

REASONS FOR DECISIONS:

 

(1)   The initial tenders that were received identified that significant cost increases are likely from the waste, recycling and street cleansing services in the next contract. The competitive dialogue procurement process allows the Council to explore service design options which may present benefits to the Council.

 

(2)   Officers have considered the initial offers from bidders and discussed opportunities for specification changes with them, which are aligned with the Council’s aims for high performance, but that will reduce the costs to the Council with minimal impacts on perceived performance.

Minutes:

N.B. This item was considered in restricted session and therefore no recordings were available.

 

The Executive Member for Recycling and Waste presented the report entitled ‘Waste, Recycling and Street Cleansing Contract Design – Part 2’.

 

Councillor Amy Allen proposed and Councillor Ian Albert seconded and, following a vote, it was:

 

RESOLVED:

 

(1)   That Cabinet agreed the service changes described in 8.2 c) of the report relating to the three-weekly collection of separated paper and cardboard predominantly in bins and the three weekly collection of the remaining dry mixed recycling (A 3,3,3 cycle as described in Appendix 3) be implemented as part of the new waste recycling and street cleansing contract which commences in 2025, the implementation date shall be delegated to the Service Director: Place in consultation with Project Board (in any event to be within four months of contract commencement).

 

(2)   That Cabinet agreed that in the event that the Council is required to make a decision to provide fortnightly collection of residual waste that the dry recycling service shall be fully commingled.

 

(3)   That Cabinet agreed the service changes described in 8.2 d) of the report relating to the removal of the requirement for a continuous street cleansing presence in town centres and moving the back to standard time to 9am be implemented as part of the new waste recycling and street cleansing contract in 2025.

 

(4)   That Cabinet agreed the service changes described in 8.2 e) relating to a removal of approximately 30% of litter bins from predominantly outside the town centres be implemented during the mobilisation of new waste recycling and street cleansing contract for 2025.

 

(5)   That Cabinet agreed the service changes described in 8.2 f) relating to a change to an input specification for high-speed road cleansing to once per year be implemented as part of the new waste recycling and street cleansing contract in 2025.

 

(6)   That Cabinet agreed the service changes described in 8.2 g) relating to the removal of dedicated seasonal leaf fall management be implemented as part of the new waste recycling and street cleansing contract in 2025.

 

(7)   That Cabinet agreed the service changes described in 8.2 h) relating to an extension of the bin delivery/repair Service Level Agreement (SLA) from 5 days to 9 days being implemented as part of the new waste recycling and street cleansing contract in 2025.

 

(8)   That Cabinet agreed the service changes described in 8.2 i) relating to an extension of the missed bin rectification SLA from 5pm the next working day to 72 hours except for missed whole streets which will remain 5pm the next working day, being implemented as part of the new waste recycling and street cleansing contract in 2025.

 

(9)   That Cabinet agreed the service changes described in 8.2 j) relating to a change in street cleansing SLAs being implemented as part of the new waste recycling and street cleansing contract in 2025.

 

(10)That Cabinet agreed the service changes described in 8.2 k) relating to reducing the number of items collected as part of bulky waste services from six to three being implemented as part of the new waste recycling and street cleansing contract in 2025.

 

(11)That Cabinet noted that the Capital expenditure identified in 10.3 of this report will need to be added to the Capital programme as part ofthe 2024/25 budget process.

 

REASONS FOR DECISIONS:

 

(1)   The initial tenders that were received identified that significant cost increases are likely from the waste, recycling and street cleansing services in the next contract. The competitive dialogue procurement process allows the Council to explore service design options which may present benefits to the Council.

 

(2)    Officers have considered the initial offers from bidders and discussed opportunities for specification changes with them, which are aligned with the Council’s aims for high performance, but that will reduce the costs to the Council with minimal impacts on perceived performance.

Supporting documents: