CHURCHGATE REGENERATION PROJECT UPDATE & NEXT STEPS - PART 1
REPORT OF DIRECTOR – ENTERPRISE
Since the previous update to Members, further work has been undertaken to assess the viability, deliverability and regeneration potential of the Churchgate site. This report provides an update on that work and seeks approval for the additional funding required to support the next phase of the project.
Decision:
RESOLVED: That Council approved the additional capital/revenue funding set out in the Part 2 report to support the single competitive procurement, comprising of two phases of a partner to assist the Council with the next stage of the Churchgate Regeneration Project.
REASONS FOR RECOMMENDATION:
(1) The Council has undertaken significant technical work, specialist studies and preliminary market engagement to inform the next stage of the Churchgate Regeneration Project.
(2) The findings indicate that further feasibility, viability and delivery planning work is required before future decisions can be taken regarding the preferred delivery model and implementation of the regeneration proposals.
(3) Approval is therefore sought for the additional funding required to undertake this next phase of work, enabling future decisions to be informed by robust technical, commercial and financial evidence.
Minutes:
Audio recording – 55 minutes 08 seconds
Councillor Tamsin Thomas, as Executive Member for Enterprise, presented Referral 6G and the report entitled ‘Churchgate Regeneration Project Update & Next Steps – Part 1’ and advised that:
· The project would deliver a redeveloped shopping centre and market, revitalised public spaces around the River Hiz, and vital footfall and housing to the area.
· Thanks were put on record to the Churchgate Project Board, Overview and Scrutiny Committee and Cabinet for their input on this stage.
· Full Council were being asked to approve funding to procure regeneration expertise to undertake detailed analysis for the project in this phase.
· Work undertaken in the last 12 months had put the project into a fundamentally more stable position as a financial and technical evidence base had been produced and a greater insight into other factors had been achieved.
· Churchgate was close to full occupancy for the first time in a while, which mirrored the strong developer confidence shown in soft market testing, but it was also recognised that it was a complex and finely balanced scheme where specialist regeneration expertise would be needed to derisk the project and remove cost elements while maintaining overall control.
· A masterplan would be formulated in this phase from the completed feasibility study, which would allow them to progress the project in a measured and controlled way while further testing viability and deliverability.
· Any uncertainty of deliverability would be decreased through this phase before a long-term decision on the project was taken.
· The ambition to deliver a high-quality regeneration scheme that secured the long-term success of Hitchin Town Centre remained unchanged.
Councillor Tamsin Thomas proposed the recommendation in the report, and this was seconded by Councillor Val Bryant.
The following Members took part in the debate:
· Councillor Sam Collins
· Councillor Ralph Muncer
· Councillor Val Bryant
· Councillor Ian Albert
· Councillor Claire Strong
· Councillor Tim Johnson
· Councillor Matt Barnes
The following points were made as part of the debate:
· Hitchin residents were fed up with the amount of time that had been spent on project planning and consultancy.
· The final part of the project was the riskiest, and they should not lose sight of what was right for the district and its residents in their approach.
· There had been a £200K overspend on consultants for the project and the administration was seeking to request substantial funding for this phase.
· The Council was fast approaching a tipping point where any future spending would be absorbed, regardless of the financial burden.
· All options including site disposal or no affordable housing provision as part of the regeneration would need to be considered to reduce the cost to the taxpayer.
· Residents of other towns and villages would be questioning whether their communities would receive a multi-million investment in a project in their area as well.
· It was desired for the project to succeed, but not at any cost.
· The project had shown transparency as there was a project board, Hitchin residents had been consulted, and 3 member briefing sessions had already taken place.
· A weekly project timetable was in place to take it into a favourable position before the creation of the new unitary authorities.
· Overspend on consultants totalled £137K, not £200K.
· A quick outcome for the project was desired, but a careful approach was needed and being taken on this fantastic opportunity.
· Reports on the Churchgate project had been given regularly at Hitchin Community Forum.
· Feasibility work proposed in this phase would inform the right choice for the project.
· The project had already cost a lot of money and would cost more going forward.
· Various feasibility studies had been undertaken in the past, and various developers had failed to develop the site and its surroundings.
· The project would have progressed a lot quicker if a developer had undertaken it.
· So many questions were unanswered and exact plans were still yet to be seen.
· This project was huge, expensive, and would be made viable through a loss of parking and housing.
· Problems relating to parking had not been sufficiently addressed, and these would need solving before progression to phase two.
In response points made during the debate, the Chair advised that this phase would ensure that the Council understood the options available to them.
In response to points made during the debate, Councillor Tamsin Thomas advised that:
· Market conditions were much different since the regeneration of Churchgate was first considered 31 years ago.
· There was evidence of a viable development route, and this should be explored.
· Hitchin was thriving, and they had an evidence base for a viable route to develop and regenerate the area.
· Members should stop worrying about what had happened in the past and focus on the future.
Having been proposed and seconded and, following a vote, it was:
RESOLVED: That Council approved the additional capital/revenue funding set out in the Part 2 report to support the single competitive procurement, comprising of two phases of a partner to assist the Council with the next stage of the Churchgate Regeneration Project.
REASONS FOR RECOMMENDATION:
(1) The Council has undertaken significant technical work, specialist studies and preliminary market engagement to inform the next stage of the Churchgate Regeneration Project.
(2) The findings indicate that further feasibility, viability and delivery planning work is required before future decisions can be taken regarding the preferred delivery model and implementation of the regeneration proposals.
(3) Approval is therefore sought for the additional funding required to undertake this next phase of work, enabling future decisions to be informed by robust technical, commercial and financial evidence.