RESOLVED:
(1) That Council approves an increase in capital expenditure of £2.4m into the capital programme for the decarbonisation work to the three leisure centres. The overall budget will be profiled across 2024/25 and 2025/26.
(2) That Council approves an increase in the capital budget of £250k for the Royston Leisure Centre (RLC) gym extension, to ensure the extension is built to net zero carbon standards.
(3) That Council approves revenue expenditure of up to £757k for termination and removal fees of the gas CHPs at North Herts Leisure Centre and Hitchin Fitness and Swimming Centre. This would be funded from General Fund reserves.
REASONS FOR DECISIONS:
(1) In May 2019, North Herts Council passed a climate emergency motion. This declaration asserted the council’s commitment toward climate action beyond current government targets and international agreements. This is currently pursued through the North Herts Climate Change Strategy 2022-2027 which sets out what the council will aim to do to reduce its own carbon emissions to achieve Carbon Neutrality for the Council’s own operations by 2030 and a Net Zero Carbon district by 2040.
(2) Gas use from our leisure centres is a significant contributor towards the Council’s own emissions. In 2022-23, gas use across the three leisure centres accounted for 1,428 tonnes CO2e. This equates to 45% of the Council’s Scope 1-3 emissions. Taking action to replace gas heating for our leisure centres with low carbon alternatives is the single most effective action we can take towards meeting our target of being carbon neutral by 2030.
(3) There is currently a capital allocation in the 2024/25 budget to build a gym extension at Royston Leisure Centre.